Skip to main content
Loading…
This section is included in your selections.

A. For all hauls where the cumulative quantity of haul is greater than 5,000 cubic yards or greater than 10,000 tons, a haul plan must specify all city streets that will be used for the haul. The haul plan shall be satisfactory to the city engineer, prior to the issuance of a grading permit.

B. For those projects a bond must be posted for $0.60/cubic yard times number of cubic yards. The actual cost for the haul shall be paid to the city after the hauling operations are complete. The final amounts shall be determined by the city engineer. A pavement engineer may be contracted by the city to conduct an investigation of the road before and after haul and submit a cost damage estimate to the city engineer for his guidance. [Code 2006 § 11-3-17].